January-February 2010

Shoring up Shoal Creek

A comprehensive attempt to revitalize an urban park in Austin, relies on measures to stabilize an eroding stream channel, better manage stormwater onsite, and restore the park landscape.

Article Tools

Create a Link to this Article

Photo: @iStockphoto.com/Ekely

Additional Article Content

By Jeffrey S Kessel

Comments


Examining the Stream Channel
Shoal Creek extends for roughly 6,400 feet within the project limits. As part of its investigation, PBS&J documented problems related to channel instability, local scouring, and bank erosion and recommended corresponding solutions. Preliminary design solutions were developed to address each known problem area.

Landmark Surveying Inc. provided surveying services, which included conducting measurements at several specific cross sections of the creek channel and noting details of each storm drain outfall and corresponding inlet within the main channel. Landmark Surveying also located all trees 8 inches or larger in diameter within the defined riparian corridor of Shoal Creek. PBS&J ecologists then identified the trees and developed a tree inventory. HVJ Associates conducted a geotechnical investigation to inform the design of such project elements as mechanically stabilized retaining walls, sloped and terraced embankments, rock riprap revetments, and water-quality structures.

Shoal Creek was divided into four separate reaches within the project limits for the channel stability analysis. The bank and channel stabilization solutions were developed based on a detailed channel assessment and stability analysis of each reach. These solutions were guided by previous studies and recently completed improvements implemented to stabilize the channel immediately upstream of the current project. The previous project served as a reference reach and provided useful data for the current restoration effort.

Photo: PBS&J
This storm drain outfall has been severely scoured and undermined by Shoal Creek.
This proposed biofiltration pond is one of 11 green infrastructure projects recommended for Pease Park.

Advertisement

Stabilizing the Banks and Channel
For each reach, PBS&J proposed solutions for stabilizing the banks and channel of Shoal Creek. A combination of eight grade-control structures and approximately 5,300 feet of bank stabilization was recommended to prevent further channel degradation and widening that threaten infrastructure and park property.

Where bank stabilization is necessary, the design goals are to develop measures that are most cost-effective (considering construction cost and long-term maintenance costs), protect the heritage trees and trail, and create the most “natural” appearance, without increasing the flood potential of Shoal Creek. For Shoal Creek, the proposed bank stabilization measures consist of three basic design approaches: graded slopes with rock toe protection, retaining walls made of stacked limestone boulders, and mechanically stabilized earth embankments.

In another effort to control channel degradation, the design includes eight low-profile grade-control structures to be constructed on the channel bottom using limestone boulders. The boulders will be configured such that the structures function as either an immovable riffle in the channel bed or drop structure. This approach was used successfully on the reference reach immediately upstream of the project site.

Assessing a Wastewater Pipeline
The presence of wastewater pipelines within the channel of Shoal Creek also must be considered as part of efforts to stabilize the stream. Approximately 1,700 feet of 18-inch-diameter wastewater pipeline located within the stream channel is under consideration for abandonment, removal, and relocation. Roughly 820 feet of the pipeline is exposed along the channel bed, while the rest is below grade. Encased in concrete, the exposed sections cause localized channel instability by directing flows into the banks and contributing to scour and bank slope failure. Scour also threatens to undermine the wastewater pipelines.

The MWM Design Group evaluated the feasibility of relocating the wastewater pipeline. The purpose of the study was to identify feasible alternative pipeline alignments outside of the creek channel and determine the associated project costs.

Based on this study, the design team recommends moving the pipeline from the channel and moving the relocated sections to the right of way along the park’s boundaries. The recommended alignment involves installing approximately 1,500 feet of 18-inch-diameter pipe within unpaved areas along the right of way of a nearby arterial that runs beside the eastern edge of the park. The report recommendations include removing the abandoned pipeline structures from the channel and installing grade-control structures to redirect flows toward the center of the channel, so as to limit the potential for head-cutting in channel sections upstream of the current pipeline locations. Next Page >

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Stormwater E-mail Updates!

Get weekly news and updates through our Stormwater e-mail newsletter!